Discipline
Client
Start Date:
In mid-2021, Seqwater, replaced a series of valves located downstream of the Cameron’s Hill Reservoir complex in an area referred to as Barnes Hill.
Engeny were engaged by Seqwater to carry out hydraulic modelling services to develop a temporary bulk network operating strategy during the valve replacement period.
The valve replacement works temporarily placed the Mt Crosby WTP offline, reducing Brisbane’s water supply capacity by approximately 50%.
The key objectives of the hydraulic modelling were to:
The outcomes of the project enabled Seqwater to safely carry out valve replacement while continuing to supply drinking water to their customers in a safe and reliable manner.
At Engeny, we’re reliable, consistent and transparent. We deliver our advice and work with precision, expertise and quality. Talk to a discipline leader in our team today and you’ll learn why so many of our clients stay with us for the long term.